Nov 1, 2021

HYDRAULIC UNIT No.4 of DNIESTER PSPP HAS RECEIVED NOMINAL CAPACITY OF 423 MW

Hydroelectric unit No. 4 "Anna" of the Dniester PSPP at night on November 9, 2021 gained a nominal capacity of 423 MW in pumping mode. The consortium "RPA "Ukrhidroenergobud "is the general contractor for the construction of the Dniester PSPP.

Sep 1, 2021

THE FIRST 200 THOUSAND kW ELECTRIC POWER OF THE HYDRAULIC UNIT No.4 OF THE DNIESTER PSPP

Hydro unit No. 4 of the Dniester PSPP (Ukrhydroenergo PJSC) produced the first 200 thousand kW⋅ of electricity. The general contractor for the construction of the Dniester PSPP is the Consortium RPA Ukrgidroenergobud.

Aug 1, 2021

START-UP OF HYDRAULIC UNIT No.4 OF DNIESTER PSPP IN GENERATOR MODE

Hydroelectric unit No. 4 Dniester PSPP (Ukrhydroenergo PJSC), was launched in the generator mode (capacity is 324 MW). This event is a great importance for the United Energy System of Ukraine, as new shunting capacities have been added. The general contractor for the construction of the Dniester PSPP is the Consortium RPA Ukrgidroenergobud.

Aug 1, 2021

WORKS ON REPLACEMENT OF BLOCK TRANSFORMERS

As part of the replacement of block power transformers 70,000 kVA (T1, T2) branch Kakhovka Neporozhny HPP PJSC Ukrhydroenergo, Consortium RPA Ukrgidroenergobud dismantled the T2 transformer (70,000 kVA).

Jul 1, 2021

TRANSFORMER T-4 IS SUPPLIED AT OPERATING VOLTAGE AT DNIESTER PSPP

At the Dniester PSPP of PJSC Ukrhydroenergo, a T-4 transformer has been put under operating voltage as part of the construction of the second stage of the largest pump storage power plant in Europe. The general contractor for the construction of the Dniester PSPP is the Consortium RPA Ukrgidroenergobud.

Jul 1, 2021

COMMISSIONING WORKS ON THE HYDRAULIC UNIT №4 DNIESTER PSPP

At the Dniester PSPP PJSC "Ukrhydroenergo" continue commissioning works on the hydraulic unit №4. The general contractor of the construction is the Consortium RPA Ukrgidroenergobud.

May 1, 2021

CONSTRUCTION OF THE SECOND STAGE OF THE DNIESTER PSPP CONTINUES

On May 28, was held a meeting which traditionally brought together the management of PJSC Ukrhydroenergo, the Consortium RPA Ukrgidroenergobud, and all subcontractors involved in the construction of the most ambitious energy project in modern Ukraine.

Jan 1, 2021

REPLACEMENT OF T4 POWER TRANSFORMER AT KANIV HPP

During the reconstruction of Unit №4 of the Kaniv HPP Branch of PJSC Ukrhydroenergo, the Consortium RPA Ukrgidroenergobud performed works on the replacement of the T4 power transformer.

Jan 1, 2021

DNIESTER PSPP: KEY MOMENTS BEFORE THE START-UP OF THE FOURTH HYDRAULIC UNIT HAVE BEEN DETERMINED

A traditional meeting was held at the Dniester PSPP, which addressed topical issues of construction of the fourth hydro unit and its preparation for commissioning. After a detailed analysis of the status of the works by a joint decision with the heads of subcontractors involved in the construction, it was determined which works should be completed on the hydraulic unit № 4 of the Dniester PSPP.