INSTALLING OF THE REINFORCED CONSTRUCTION OF THE CRANE BEAM (HYDROGENERATING UNIT NO. 4 OF THE DNIESTER PSPP)

INSTALLING OF THE REINFORCED CONSTRUCTION OF THE CRANE BEAM (HYDROGENERATING UNIT NO. 4 OF THE DNIESTER PSPP)

On April, 2018 the Сonsortium RPA Ukrgidroenergobud has installed the reinforced construction of the crane beam over the hydrogenerating unit No. 4 of the Dniester pumped storage power plant into the design position. The weight of the reinforced construction is 25.2 tons.

On April, 2018 the Сonsortium RPA Ukrgidroenergobud has installed the reinforced construction of the crane beam over the hydrogenerating unit No. 4 of the Dniester pumped storage power plant into the design position. The weight of the reinforced construction is 25.2 tons.